Vatika Mindscapes, Mathura Road

22 / Aug / 2016

Tower A occupied by Client

22 / Aug / 2016

Tower B 6th floor client office(JSS) operational since 28th Dec 2015 and other floors are also ready for Client fit out.

22 / Aug / 2016

Tower C pour-1 10th floor slab shuttering work is in progress and pour-2 9th to 10th floor vertical is in progress.

22 / Aug / 2016

Tower D 9th floor Pour-1 slab casting complete. Pour-2 slab shuttering is in progress. 9th to 10th floor Pour -1 vertical casting is in progress.